Receiving inspection checklist
Upon delivery, check: sheet count matches packing list; no visible transit damage; film surface is scratch-free on 90% of sheets; edge sealant is present on all four sides; MTC or CoO documents are in the envelope. Reject batches with more than 5% edge-seal defects or visible core gaps.
Density and thickness verification
Randomly weigh 3 sheets per 100 delivered. Target 29-32 kg for 18mm hardwood core. Measure thickness at 4 points per sheet with a digital caliper; tolerance should be within +/- 0.5mm of nominal. Record readings in the site log for traceability.
On-site storage requirements
Store horizontally on level timbers or pallets, never directly on sand or concrete. Cover with a breathable tarp, not plastic sheeting that traps condensation. In UAE summer, avoid storage against south-facing walls where panels can reach 60°C and soften the film adhesive.
Handling and reuse tracking
Lift panels by the edges, not by flexing the centre. Clean concrete residue immediately after stripping with a wooden scraper and water; avoid metal tools that gouge the film. Mark each panel with its pour count so the foreman retires it before delamination risk rises.
Cutting and edge re-sealing protocol
Every site-cut panel must have its exposed core re-sealed with waterborne acrylic within 24 hours. Maintain a dedicated brush and sealant bucket at the cutting station. Unsealed cuts are the fastest route to moisture ingress and panel failure.